How long does it take to produce a commercial?
Six to ten weeks is normal. The shoot is two days of it.
The timeline
- Weeks 1–2
- Brief, concept development, treatment and budget approval.
- Weeks 3–4
- Scripting, storyboards, casting, location scouting and the PPM.
- Week 5
- Shoot. One to three days for most commercials.
- Weeks 6–7
- Offline edit and client review rounds.
- Weeks 8–9
- Grade, sound design, music, VFX and versioning.
- Week 10
- Final master, broadcast compliance and delivery of all cutdowns.
What can be compressed
Concept development, if you arrive with a clear single-minded brief rather than three directions to explore.
Casting, when you accept a smaller shortlist or use talent you have worked with before.
Post, by booking the edit and grade in advance rather than starting the search after the shoot wraps.
Approvals, by naming one decision-maker before the project starts. This is usually the single largest saving available.
What cannot
Location permits and clearances run on other people's calendars.
Talent availability and usage negotiation take as long as they take.
Broadcast compliance has a fixed turnaround and sits at the end, where there is no slack left.
Original music composition needs weeks, not days. If the schedule is tight, licence a track and decide that early.
Working backwards
Start at the air date and subtract. Broadcast delivery needs a week of headroom. Post needs four. The shoot needs a fixed date that talent and locations are held against. Pre-production needs four weeks before that.
If the maths does not work, the honest options are fewer deliverables, a simpler concept or a later date. Compressing approvals is the only free lever, and it is usually the one nobody uses.